Concrete Quantities

Materials for slabs, beams, footings and columns.

Step 1 · New to this? Start here

The basics

Concrete is cement, sand and ballast mixed with water. A mix ratio such as 1:2:4 means 1 part cement, 2 parts sand and 4 parts ballast by volume.

First you find the volume of the element you are casting: length x width x depth. That is the wet volume, the concrete you end up with in the formwork.

Dry materials shrink when water is added, because the sand fills the gaps in the ballast and the cement fills the gaps in the sand. So you need more dry material than the wet volume. On site we multiply by 1.54 to get the dry volume.

The dry volume is then shared out using the mix ratio. One 50 kg bag of cement is about 0.0347 m³, which is how we turn the cement volume into bags.

Wet volume
The finished concrete volume: L x W x D.
Dry volume
Wet volume x 1.54. The loose materials you actually buy.
Mix ratio
Cement : sand : ballast by volume. 1:2:4 is about C20, used for most slabs and beams.
Ballast
Crushed stone aggregate, also called coarse aggregate.
Wastage
Extra for spillage and uneven formwork. 5% is common.

Step 2

How to use this calculator

  1. 1Measure the element: length and width in metres, and depth (thickness) in metres. A 150 mm slab is 0.15 m.
  2. 2Choose the mix ratio given on the structural drawing or specification. If it says C20, use 1:2:4.
  3. 3Leave wastage at 5% unless your site loses more.
  4. 4Read the cement bags first. That is usually the biggest cost.
  5. 5Read sand and ballast in m³ and in tonnes. Use whichever unit your supplier sells in.

Step 3 · Enter your numbers

Results

Cement (50 kg bags)
20 bags
Wet volume
3.15 m³
Dry volume
4.85 m³
Sand
1.39 m³
Sand (weight)
2.22 tonnes
Ballast
2.77 m³
Ballast (weight)
4.16 tonnes

Estimates for learning and planning. Always confirm quantities with your engineer or quantity surveyor.

Step 4 · Check your understanding

Worked example

A ground floor slab is 5 m long, 4 m wide and 150 mm thick, using a 1:2:4 mix.

  1. 1. Wet volume = 5 x 4 x 0.15 = 3.0 m³, plus 5% = 3.15 m³
  2. 2. Dry volume = 3.15 x 1.54 = 4.85 m³
  3. 3. Total parts = 1 + 2 + 4 = 7
  4. 4. Cement = 4.85 x 1/7 = 0.693 m³, and 0.693 / 0.0347 = 19.97, round up to 20 bags
  5. 5. Sand = 4.85 x 2/7 = 1.39 m³ (about 2.22 tonnes)
  6. 6. Ballast = 4.85 x 4/7 = 2.77 m³ (about 4.16 tonnes)

Order 20 bags of cement, about 1.39 m³ of sand and 2.77 m³ of ballast.

Common mistakes to avoid

  • Entering depth in mm instead of metres. 150 mm must be typed as 0.15.
  • Using the wet volume to buy materials. Always use the dry volume.
  • Guessing the mix. The structural drawing tells you the concrete class. Use it.
How it's calculated
  • Wet volume = L × W × D × (1 + wastage/100)
  • Dry volume = wet volume × 1.54
  • Sum = c + s + b
  • Cement bags = (dry × c / sum) / 0.0347, rounded up
  • Sand = dry × s / sum (1.6 t/m³)
  • Ballast = dry × b / sum (1.5 t/m³)