Excavation Volume
Trenches, pits and basements — volume and cart-away.
Step 1 · New to this? Start here
The basics
Before any foundation goes in, the ground has to be dug out. The size of the hole is length x width x depth. This is the bank volume, the soil as it sat in the ground.
Once soil is dug, it loosens up and takes more space. This is called bulking, and it is usually 20 to 30% for ordinary soil. The loose volume is what has to be loaded onto lorries and carted away.
So you need both numbers: bank volume to price the digging, loose volume to plan the transport.
- Bank volume
- Undisturbed soil in the ground: L x W x D.
- Bulking
- How much the soil swells once dug. 25% is a fair default for ordinary soil.
- Loose volume
- Bank volume x (1 + bulking/100).
- Tipper trip
- One lorry load. The calculator assumes 10 m³ per trip. Ask your transporter for their lorry size.
Step 2
How to use this calculator
- 1Enter the length of the trench or pit. For a strip foundation, use the total centre-line length of all the trenches.
- 2Enter the width and depth from the foundation drawing, in metres.
- 3Leave bulking at 25% unless your soil is rock or very clayey, where it can be higher.
- 4Read the loose volume. That is the soil you will have to move or store.
- 5Read the tipper trips to plan and budget cart-away.
Step 3 · Enter your numbers
Results
Estimates for learning and planning. Always confirm quantities with your engineer or quantity surveyor.
Step 4 · Check your understanding
Worked example
The 4 m x 3 m room needs a strip foundation trench along all four walls, 0.6 m wide and 1.0 m deep.
- 1. Trench length = 4 + 3 + 4 + 3 = 14 m
- 2. Bank volume = 14 x 0.6 x 1.0 = 8.4 m³
- 3. Loose volume = 8.4 x 1.25 = 10.5 m³
- 4. Trips = 10.5 / 10 = 1.05, round up to 2 trips
You dig 8.4 m³ but cart away 10.5 m³, which is 2 tipper trips. Some of it can stay on site for backfilling.
Common mistakes to avoid
- Using bank volume to book lorries. Always plan transport on the loose volume.
- Forgetting working space. If the drawing asks for extra width for formwork, include it.
- Carting away everything. Keep enough good soil for backfilling around the foundation.
How it's calculated
- Bank volume = L × W × D
- Loose volume = bank × (1 + bulking/100)
- Tipper trips = loose / 10, rounded up