All calculators

Roofing Sheets (Mabati)

Count roofing sheets for a lean-to or gable roof. Effective cover width depends on the sheet profile, so check it with your supplier.

Step 1 · New to this? Start here

The basics

Roofing sheets (mabati) are laid side by side along the length of the roof, with each sheet overlapping the next. So the number of sheets per slope depends on the roof length along the ridge and how much width each sheet actually covers once it overlaps.

That covered width is called the effective cover width. A sheet might be 0.9 m wide but only cover about 0.76 m after the overlap. It depends on the profile, so always check it with your supplier.

Sheet length runs from the ridge down to the eaves, plus an overhang. You can order sheets cut to length, so you buy one sheet per strip for each slope.

Ridge
The top line where the two slopes of a gable roof meet.
Effective cover
The width one sheet covers after overlapping its neighbour.
Gable roof
Two slopes meeting at the ridge. A lean-to (mono-pitch) has one.
Ridge capping
The folded sheet that covers the ridge. You need its length in metres.

Step 2

How to use this calculator

  1. 1Enter the roof length along the ridge in metres.
  2. 2Enter the sheet length per slope, from ridge to eaves including the overhang. The worked example shows how to get it from the drawing.
  3. 3Choose 1 slope for a lean-to or 2 for a gable roof.
  4. 4Enter the effective cover width from your supplier, or keep 0.76 m.
  5. 5Read total sheets, roof area and ridge capping length.

Step 3 · Enter your numbers

Results

Total sheets
30 sheets
Sheets per slope
14 sheets
Total roof area
80.00 m²
Ridge capping length
10.00 m

Estimates for learning and planning. Always confirm quantities with your engineer or quantity surveyor.

Step 4 · Check your understanding

Worked example

A house is 10 m long and 7 m wide, with a gable roof at 25 degrees and a 0.6 m overhang.

  1. 1. Half the width = 3.5 m. Slope length = 3.5 / cos 25° = 3.5 / 0.906 = 3.86 m
  2. 2. Sheet length = 3.86 + 0.6 overhang = 4.46 m, so order 4.5 m sheets
  3. 3. Sheets per slope = 10 / 0.76 = 13.2, round up to 14
  4. 4. Total = 14 x 2 slopes = 28, plus 5% = 29.4, round up to 30 sheets
  5. 5. Ridge capping = 10 m

Order 30 sheets cut to 4.5 m, plus 10 m of ridge capping. Enter 10, 4.5, 2 slopes and 0.76 to see the same result.

Common mistakes to avoid

  • Using the full sheet width instead of the effective cover. You will come out short.
  • Measuring the sheet length on the plan. The plan shows the flat width, but the roof slopes, so the sheet is always longer.
  • Forgetting the overhang at the eaves.
How it's calculated
  • Sheets per slope = ridge length ÷ effective cover width, rounded up
  • Total sheets = sheets per slope × slopes × (1 + wastage/100), rounded up
  • Roof area = ridge length × sheet length × slopes
  • Ridge capping = ridge length (gable roofs only)